Bundy Canyon Rd. Improvement Project (Segment 1), CIP 026-1


Updated: 5/4/2023

The City of Wildomar has completed pavement improvements and the majority of striping, with minor striping and signage, and sections of AC Curb remaining. The anticipated remaining duration for final construction punchlist items is 2 weeks.

The installation of traffic signals at Sellers Rd. and Monte Vista Rd. are completed and are now in operation.

 
East Project Limits


Feel free to contact the City if you have any questions or concerns.

Remaining Schedule:  

        • Estimated Project Completion: Early May

General Updates

Pavement improvements throughout the project began in September 2022, with the first section of new asphalt completed on the south side of Bundy Canyon Rd. and the second section on the north side beginning in October. Detour signs will remain in place to direct drivers around the current closures until intersections are reopened.

Please use caution when driving through the construction area, and please follow all traffic control signs and direction from project traffic control personnel.

Please expect delays when driving through the construction area. Construction Zone speed limits are strictly enforced.


Questions or Concerns

Please contact Cameron Luna, Project Manager, regarding any questions or concerns related to this project.

 

Project Summary

The Bundy Canyon Rd. Improvement Project, Segment 1, includes the widening of Bundy Canyon Rd. from Cherry St. to approximately 1600' east of Oak Canyon Dr. The existing road will be widened from two lanes to four lanes, with turn lanes. Bike lanes will be included from the I-15 freeway northbound ramps to Monte Vista Dr., where the bike lanes will connect to a future Class 1 pedestrian and bicycle trail, planned for construction in the next few years. Improvements will also include new sidewalks, new storm drains, and other related roadway improvements. Two new traffic signals will also be installed at the intersections of Sellers Rd. and at Monte Vista Dr.

 

Project Schedule & Contractor Info

  • Construction originally began in April 2021 and is expected to be complete in April 2023.
  • Contractor for Phase I of the Bundy Canyon project is James Mcminn Inc. (JMI)


Project Funding

The total estimated construction cost is approximately $7,774,445.00.

Project Funding Sources include:

  • Measure AA
  • RCTC (Riverside County Transportation Commission)
  • TUMF (Transportation Uniform Mitigation Fee)
  • Riverside County Flood Control and Water Conservation District (RCFC&WCD)
  • Local Grants (RCTC SB 821 funds)
  • EVMWD Cooperative Agreement (Elsinore Valley Municipal Water District)
  • Development Impact Fees
  • Developer Cash-in-Lieu Contributions

 

Relevant Project Documents

  • Project Budget and Fact Sheet from 5-Year CIP Program:
  • City Council Meeting Project Update Presentations:

  • Monthly City Newsletter Updates:
  • Video Updates:


    Project Exhibit

     Bundy Canyon Project Limits