Lennar Homes - Horizons
Update (1/26/2022):
- Backbone dry utility installation and backfill on Elizabeth Lane completed.
- Onsite dry utility backbone installation will be completed approximately 1-27-23
- Work Order 1 (phases Models, 1-3 onsite) curb and gutter and streets paved approximately 1-31-23.
- Model homes will be complete 2-17-23
- Model grand opening 2-25-23
- Phase 1 Production Homes to start onsite trenching on 2-10-23
Please see 'Overall Project Schedule' below for additional details.
Update (1/10/23):
- On hold due to rain event.
Update (1/3/23):
- On hold due to rain event.
Update (12/27/22):
- On hold due to rain event.
Update (12/12/22):
- Elizabeth Lane is currently under construction.
- Onsite streets are almost complete.
- Model homes are under construction.
- Production units have started construction.
Update (11/23/22):
Update (10/28/22):
- Prielipp construction is complete and is fully open to through traffic.
- Improvements on Elizabeth Lane are in progress.
Update (9/30/22):
- Prielipp construction is still underway. Base paving and compaction are complete. Procurement of AC and concrete has delayed completion again, due to supply chain issues. We sincerely apologize for the inconvenience, and are working onsite with the developer and their contractor to assist however we can so the construction can be completed as quickly as possible, and the road reopened to through traffic.
Update (9/22/22):
- Prielipp construction is underway. Completion still expected the week of 9/30, pending no additional field issues.
Update (9/15/2022):
- Headwall for storm drain facilities currently under construction.
- Prielipp widening and improvements expected to begin in the next few weeks.
Update (9/7/2022):
Update (8/31/2022):
- Contractor will be working on fire hydrant tie-ins.
- Curb and gutter staking for Prielipp and Elizabeth will be installed.
- Construction of curb and gutter will be followed by street improvements.
Update (8/25/22)
- No new updates. Project schedule updated on 8/17/22 is still current.
Update (8/17/22)
- All storm drain in Prielipp Road has been constructed.
- Relocation of fire hydrants along Prielipp is underway.
- Domestic water construction in Elizabeth Lane is underway.
- Wet utilities at the Prielipp and Elizabeth Lane intersection are complete.
- Headwall/retaining wall for drainage outlet structure along Prielipp is scheduled for construction within the next two weeks.
- After completion of headwall/retaining wall, paving/widening on Prielipp can commence.
Update (7/22/22):
- All in-tract sewer proposed completion early next week.
- Water line construction set to begin next week.
- Dry utility construction will begin at the end of August.
- In-tract curb and gutter construction will begin next week.
- Contractor will begin recertifying all pads due to erosion.
Overall Project Schedule (Updated on 9/30/22):
Beazer Homes, Boulder Creek
Update (1/26/2023):
Offsite Improvements
- 1/30/23 (tentative) – Culvert start,epending on how wet it is.
- 2/10//23 - Rule 20 on Grand Ave, SCE to have energized from overhead to underground.
- 2/27/23 – Start grading street shoulder for paving, on Grand Ave.
In Tract work
- Phases 3-5 under construction.
- Phase 6 – Start 2/6/23.
Please see 'Overall Project Schedule' below for additional details.
Update (1/10/23):
- On hold due to rain event.
Update (1/3/23):
- On hold due to rain event.
Update (12/27/22):
- On hold due to rain event.
Update (12/12/22):
Update (11/23/22):
Update (10/28/22):
- Construction of improvements on McVicar between Grand and Whispering Way are complete.
- SCE facilities in Grand are in the process of being relocated.
- Construction of improvements on Grand has commenced within the area that is already closed to through traffic.
Update (9/15/2022):
- Partial re-opening of McVicar Street from Whispering Way to Grand Avenue
- Curb and Gutter on Grand is 50% complete.
- No updates on the project schedule.
Update (9/7/2022):
- Off Tract Improvements
- Grand Avenue – pouring curb and gutter
- McVicar Street from Grand Avenue to Whispering Way – street improvement work
- No updates on the project schedule.
Update (9/1/2022):
- No new updates. Project Schedule below has been updated.
Update (8/24/2022):
- Edison de-energizing facilities at culvert: a portion has been de-energize, waiting for a portion with street light facilities and facilities running under culvert. ETA for this is 9/30/22.
- The goal is to have McVicar 100% open and paved completely over culvert by 2/28/23.
Update (8/17/22):
- Construction of storm drain connections at the intersection of Grand and McVicar is in progress and should be completed by the end of the week.
- McVicar utilities are complete, with the exception of the RCFC box culvert (master planned facilities), and is now base paved with curb and gutter almost complete.
- Curb and gutter is being constructed on Grand, and relocation of SCE poles will soon follow.
Update (7/22/22):
- Working on Storm Drain in McVicar in coordination with RCFC in field. Projected start of construction for box culvert, at the end of August.
- BMPs, graffiti, and traffic control was in disarray – everything has been cleaned up as of today.
- Traffic Control on McVicar has been updated per City Traffic Engineer’s request.
Overall Project Schedule (Updated 9/1/22):
Baxter Village
Update (1/26/23):
- Working on transitional paving from the old WIldomar Trail to the new road this week. A portion of the new road will be completed and striped for use by 1/27.
- Baxter Road will be closed from 1/26 though March to construct infrastructure and new roads (Margaret Lane and Baxter Road).
- Message boards have been updated to reflect the new closures, and flag-men are in place and at the ready.
Please see 'Overall Project Schedule' below for additional details.
Update (1/10/23):
- On hold due to rain event.
Update (1/3/23):
- On hold due to rain event.
Update (12/27/22):
- On hold due to rain event.
Update (12/12/22):
- Wildomar Trail widening is in process.
Update (11/23/22):
Update (10/28/22):
- Utilities across Wildomar Trail are complete.
- Wildomar Trail street widening has commenced.
Update (9/15/2022):
- Installation of utility laterals across Wildomar Trail.
Update (8/31, 9/1/2022):
Update (8/25/22):
- First phase of new road paving is projected to begin on 9/13/22.
- First phase of Wildomar road crossing of wet utilities to be completed by 8/26/22.
- Contractor might need a day or two of lane closures during the week of 9/6 for dry utilities (landscape sleeves, traffic, street light conduits and communication cables.
- Contractor will be making lane changes the week of 9/13 during paving operations per traffic control plans.
Update (8/17/22):
- Water and storm drain line construction with traffic crossing Wildomar Trail scheduled for 8/18 through 8/30.
- First section of paving on Wildomar Trail is scheduled to begin on or around 9/13/22.
Update (7/22/22):
- Sewer and water line work across Wildomar Trail will begin next Tuesday-7/26-Wednesday, 7/27 during the hours of 9:00 am-2:00 pm. Sewer will begin first.
- Road depression at project truck crossing will be fixed at the same time.
- All work will utilize the existing lane closure with flagmen & traffic control.
- Traffic plates will be anchored and welded for safety and will remain in place until the new road witches over.
- Waterline construction is scheduled to commence after sewer is complete.
Overall Project Schedule (No change from 8/18/22):
KB Homes - Verano
Update (1/10/23):
- On hold due to rain event.
Please see 'Overall Project Schedule' below for additional details.
Update (1/3/23):
- On hold due to rain event.
Update (12/27/22):
- On hold due to rain event.
Update (12/12/22):
Update (11/23/22):
- Production phases have started construction.
Update (10/28/22):
- Interior streets are paved.
- Models have been constructed.
Update (9/15/2022):
Update (9/7/2022):
Update (8/31/2022):
- No new updates. Project Schedule below has been updated.
Update (8/24/2022):
- No new updates. Project Schedule below has been updated with completed work.
Update (8/17/22):
- Construction of shoulder improvements on Summer Sage Way are nearing completion.
- In-tract sewer, water, and storm drain are currently under construction.
Overall Project Schedule (Updated on 8/31/22):
IVMC Expansion Project
Update (1/10/23):
Please see 'Overall Project Schedule' below for additional details.
Update (1/3/23):
Update (12/27/22):
Update (12/12/22):
Update (9/15/2022):
Update (8/29/22):
- The temporary parking lot at Yamas and Prielipp will no have any road closures associated with the work.
- 2nd approach was poured on 8/24/22 since material was released early.
- Site work was scheduled to be completed Friday 8/25 and the project will be turned over for use.
Update (8/18/22):
- DPR Construction-directed work is all occurring on-site at the Inland Valley Medical Center campus.
- Ongoing activities are mainly grading activities, with various underground utility work ongoing and some of the temporary infrastructure work for the buildings (under HCAI permits).
- It has been reported that the temporary parking lot at Prielipp and Yamas is scheduled for completion by the end of August.
Overall Project Schedule: